1
|
|
2
|
- MAX has run the Fednet peer point for Abilene, vBNS, DREN, NISN, NREN,
USGS for 4 years
- Previously called NGIX/East coast, is meet-me point (NAP) for major
Federal R&E nets.
- Topology was full L2 mesh of p-t-p atm pvcs. No transit peerings, no
common route pool. Doesn’t scale
to larger peer points, but kept life simple.
- Then atm began to go out of style, and customer nets began push for
frame-based (gige) peering
|
3
|
- We contemplated several architectures, including putting all nets on
Junipers directly and using transitional cross-connects (tccs) that
allow bolting ethernets to atms to sonets.
- Ended up deciding to use conventional switch, because of high cost of
10G router interfaces ($110k vs $30k for switched), also no tcc IPv6.
- Did side-by-side comparison of Cisco 6500 vs Extreme Black Diamond. Liked Extremes, but no oc12 atm, and
winning feature was Cisco’s OSM-2OC12-atm 1483 bridged-routing blade
|
4
|
- One of the many reasons in addition to lane why people run screaming
from atm (actually, if you only do pvcs, atm is easy and reliable AND
can do 9K and even 64k mtus). I’m
no 1483 expert.
- There are many variations involving routed and bridged pdus. Basically, bridged is used by SPs who
need to connect ethernets via an atm cloud. What Marconi’s gige int does: useless
for us. Juniper does minimal
routed subset w/1 ip addr good only for dslams. Others as well, complex.
|
5
|
- There are several variants of routed pdus across different platforms,
mostly also useless to us.
- But on 6500 OSM blades Cisco has developed a 1483 bridged/routed encap
that does just what we wanted: allow ethernets to connect to atms. Uses proxy arp and other ugly stuff
internally.
- Best part was that we only needed it for the transition, so we borrowed
the $60K blade for 6 months & then returned it when all atm gone.
|
6
|
- Converting a national NAP from atm to gige isn’t like changing over your
campus net at midnight.
Replacement lines have to be arranged, peer partners have to
coordinate ints, downtime has to be minimal because they’re paying for
uptime
- The biggest issue was how to do the transition without massive flag-day
changeover nightmare
- With testing, realized that the Cisco OSM blade bridged-routing would
allow us to single-endedly change over each peer at midnight without any
of their full-mesh of peers needing to be there.
|
7
|
- We hooked up both OSM OC12 atms
to the Marconi atm switch (would have been a problem if more traffic
than would fit, but there wasn’t).
- All peers were assigned new vlans matched to their old pvcs. The 6500 bridged routed encap allowed
us to make ip connections across.
In some sense was subset of TCCs, but cheaper.
- When each peer had their new line and gige int ready with new vlans, we
hot-cut their line both ends to gige, moving the /30 w/o peers knowing!
|
8
|
- interface ATM4/1
- description marconi 1D1
- mtu 9186
- no ip address
- atm bridge-enable
- switchport trunk allowed vlan
161,170,178
- switchport mode trunk
- interface ATM4/1.161 point-to-point
- pvc USGS-Abilene 161/32
- bre-connect 161
- interface GigabitEthernet3/5
- description USGS
- mtu 9216
- no ip address
- switchport trunk encapsulation
dot1q
- switchport trunk allowed vlan
158,161,162,178
- switchport mode trunk
- interface Vlan161
- description ABIL-USGS ACTIVE gige
- no ip address
- mtu 9216
|
9
|
- Of course there was,
- Overall had to be VERY careful at midnight cutting pvcs
- Testing initially didn’t work, took conf with Cisco product manager to
resolve issues. Then fine. Had incredible lab juryrig of atm
switch & routers in multiple bldgs
- NASA’s NISN was first, easy because had spare fiber to GSFC, didn’t have
to hotcut.
- Then Abilene was easy, because MAX sells them lambda transport to NGIX,
just had change wdm
- USGS, NLM, and MAX also easy hotcuts.
- But MCI’s DREN and vBNS were nightmare.
|
10
|
- Caveat: MCI did VERY good job,
not their fault.
- MCI is contractor for both original vBNS and in 2002 brought up new
DREN. MCI had Verizon OC12 from
their pop to MAX for years, I suggested both share it.
- With summer gige conversion, were unable to get replacement gige line to
their pop. Decided keep OC12atm
and I installed their colo M10 to run TCCs.
- Juniper and Andrea Reitzel tested in lab, worked
- At midnight cut, vBNS TCCs failed, had to back out 5am. Eventually had to loan MCI MAX on-site
test routers.
- Scott Robohn of Juniper found,needed old gige firmware
- After another 4am-er got working, but tccs still touchy
|
11
|
- All peers off atm, the OSM blade went back
- Now the config is totally boring, pure L2 on one 16-port gige blade,
runs beautifully.
- Will be upgrading Abilene’s peering to 10G next week, already tested
Luxn 10G transponders.
- NREN joined NGIX, using GSFC wdm transport
- Subsequently bought lab 6503 to test future IOSes and other changes.
Upcoming release will have L2 support for netflow, now just int stats.
|
12
|
- Dan Magorian
- magorian@maxgiapop.net
|